Construction update · as of

Construction update October 2026: ahead of schedule – interior 80 % complete

Rendering of the finished student residence at Starzenbachweg 16, Deggendorf
Rendering: how the building will look once it is finished.

Work at Starzenbachweg 16 is progressing well. The shell is complete. The exterior works are 95 % complete – only the fences are still missing. Interior finishing is 80 % complete: screed, painting and tiling are done; flooring, bathrooms and doors are now under way.

We are ahead of schedule and fully expect completion at the end of February 2027. You can move in no later than 1 April 2027 – by arrangement already during March 2027, around the start of the summer semester.

Progress at a glance

We are ahead of schedule.

  1. doneShell constructioncomplete
  2. doneScreed, painting, tilingdone
  3. in progressExterior95 % completeonly the fences left
  4. in progressInterior finishing80 % completeflooring, bathrooms, doors under way
  5. scheduledCompletionend of February 2027
  6. scheduledMove-induring March 2027 by arrangement, no later than 1 April 2027