Construction update · as of
Construction update October 2026: ahead of schedule – interior 80 % complete
Work at Starzenbachweg 16 is progressing well. The shell is complete. The exterior works are 95 % complete – only the fences are still missing. Interior finishing is 80 % complete: screed, painting and tiling are done; flooring, bathrooms and doors are now under way.
We are ahead of schedule and fully expect completion at the end of February 2027. You can move in no later than 1 April 2027 – by arrangement already during March 2027, around the start of the summer semester.
Progress at a glance
We are ahead of schedule.
- doneShell constructioncomplete
- doneScreed, painting, tilingdone
- in progressExterior95 % completeonly the fences left
- in progressInterior finishing80 % completeflooring, bathrooms, doors under way
- scheduledCompletionend of February 2027
- scheduledMove-induring March 2027 by arrangement, no later than 1 April 2027